TR 2008/10: Petroleum
resource rent tax: application of Petroleum Resource Rent Tax
Assessment Regulations 2005 to an integrated gas-to-liquid
operation
|
Contents |
Para |
|
What this Ruling is about |
1 |
|
Background |
2 |
|
Ruling |
12 |
|
Examples |
33 |
|
Date of effect |
43 |
|
NOT LEGALLY BINDING SECTION: |
|
|
Appendix 1: |
|
|
Explanation |
44 |
|
Appendix 2: |
|
|
Alternative views |
100 |
|
Appendix 3: |
|
|
Detailed contents list |
107 |
|
This
publication provides you with the following level of
protection:
This publication (excluding appendixes) is a public
ruling for the purposes of the Taxation
Administration Act 1953.
A public ruling is an expression of the Commissioner's
opinion about the way in which a relevant provision
applies, or would apply, to entities generally or to a
class of entities in relation to a particular scheme or
a class of schemes.
If you rely on this ruling, we must apply the law to you
in the way set out in the ruling (unless we are
satisfied that the ruling is incorrect and disadvantages
you, in which case we may apply the law in a way that is
more favourable for you - provided we are not prevented
from doing so by a time limit imposed by the law). You
will be protected from having to pay any underpaid tax,
penalty or interest in respect of the matters covered by
this ruling if it turns out that it does not correctly
state how the relevant provision applies to you. |
What this Ruling is about
1. This Ruling explains aspects of how the relevant Petroleum
Resource Rent Tax Assessment Regulations 2005 (PRRTA
Regulations) are to be interpreted in determining the assessable
petroleum receipts of a taxpayer for the sales gas from a
petroleum project produced and processed in an integrated
gas-to-liquid (GTL) operation (which exists in circumstances
defined in subregulation 4(1) of the PRRTA Regulations). This
Ruling covers the following topics:
-
·
-
the definition and measurement of the
volume of project sales gas (for example, represented as
VG in regulation 17 of the PRRTA Regulations);
-
·
-
the definitions of project product, phase
and energy coefficient;
-
·
-
the definition and measurement of the
volume of project natural gas (for example, represented
as VA and VB in regulation 10 of the PRRTA Regulations);
and
-
·
-
the measurement of gas and liquid volumes.
Background
2. Petroleum resource rent tax (PRRT) payable under the Petroleum
Resource Rent Tax Assessment Act 1987 (PRRTAA)
is assessed on a petroleum project basis. Under section 21 of
the PRRTAA, the tax is imposed on the taxable profit of a
taxpayer for a year of tax in relation to a project. The taxable
profit of a taxpayer is calculated from the assessable receipts
and the deductible expenditure of the taxpayer for a year of
tax. The assessable receipts derived by a taxpayer in a year of
tax include assessable petroleum receipts (subsection 23(1) of
the PRRTAA).
3. Assessable receipts arise when a marketable petroleum
commodity (MPC) under the PRRTAA, or petroleum under the PRRTAA
from which no such commodity has been produced, is sold.
Assessable receipts also arise when an MPC is further processed
or treated or is otherwise moved away from its place of
production (or adjacent storage), so far as no assessable
receipts have already arisen (sections 24 and 25 of the PRRTAA,
and the definition of 'excluded commodity' in section 2 of the
PRRTAA). For sales gas from a petroleum project that becomes an
excluded commodity by being sold other than at arm's length, or
without being sold, the assessable receipts for that sales gas
are worked out in accordance with the regulations (paragraphs
24(1)(d) and (e) of the PRRTAA).
4. In an integrated GTL operation, the petroleum recovered from
a petroleum project is processed into sales gas which is then
processed into liquefied product. Other MPCs (usually
condensate) may also be produced as separate products.
Generally, there is no arm's length sale of sales gas in an
integrated GTL operation. If this is the case, then pursuant to
subsection 24(1) of the PRRTAA, the assessable petroleum
receipts of a taxpayer for the sales gas produced and processed
in the integrated GTL operation in a year of tax are determined
by applying the PRRTA Regulations. Where there is an arm's
length sale of sales gas from a petroleum project, the
assessable petroleum receipts for that gas will be calculated by
applying paragraph 24(1)(b) of the PRRTAA. Where the taxpayer is
not a participant in an integrated GTL operation or the sales
gas is not project sales gas of that operation, the assessable
petroleum receipts will be calculated as if the sales gas were
any other MPC (subregulations 14(3) and 15(3) of the PRRTA
Regulations).
5. The PRRTA Regulations apply to determine the assessable
petroleum receipts of a taxpayer for their project sales gas, in
relation to a petroleum project that is an integrated GTL
operation (paragraphs 24(1)(d) and (e) of the PRRTAA and
regulations 14 and 15 of the PRRTA Regulations). If project
sales gas of the integrated GTL operation is the subject of a
non arm's length sale, the assessable petroleum receipts are
determined by applying regulation 16 of the PRRTA Regulations to
the gas. If project sales gas of the integrated GTL operation is
not sold, the assessable petroleum receipts for the gas are
determined by applying regulation 17 of the PRRTA Regulations.
6. If an advance pricing arrangement (APA) applies, the
assessable petroleum receipts of the taxpayer are calculated in
accordance with the APA (sub-subregulations 16(1)(a) and
17(1)(a) of the PRRTA Regulations). Where there is no APA, but
there is a comparable uncontrolled price (CUP), the assessable
petroleum receipts are calculated by applying the CUP (or, for a
non-arm's length sale for a higher amount, at that higher
amount) (sub-subregulations 16(1)(b) and 17(1)(b) of the PRRTA
Regulations). Because the CUP price is to be applied to the
relevant volume of project sales gas (under sub-subregulation
16(2)(a) and subregulation 17(2) of the PRRTA Regulations), a
CUP must always be worked out as a price for a volume of gas. So
far as no APA applies and no CUP is available, then a price
(called the residual pricing method (RPM) price), determined by
applying the RPM prescribed in regulation 25 of the PRRTA
Regulations, must be used. That method produces a price applied
per volume of gas under sub-subregulation 16(3)(a) and
subregulation 17(3) of the PRRTA Regulations.
7. In an integrated GTL operation, petroleum (natural gas) is
processed into sales gas (an MPC, for which an assessable
receipt arises in calculating PRRT), or the petroleum is used up
in doing so. The sales gas that is part of the integrated GTL
operation, the project sales gas, is processed into project
liquid (the LNG and other liquefied gas products of the
integrated GTL operation, which are generally sold by the
operation), or the project sales gas is used up in doing so. The
processing of project petroleum to produce project sales gas is
referred to as the upstream stage and the processing of project
sales gas into project liquid is referred to as the downstream
stage. Because PRRT applies on the basis of the assessable
receipt arising or taken to arise for the sales gas, that
receipt needs to be worked out where the sales gas is not sold
at arm's length. The PRRT Regulations include the RPM as a way
to do so. The RPM price incorporates cost-plus and netback
calculations to value the sales gas (see Figure 1). The
cost-plus and netback calculations are two of the most readily
utilised and recognised kinds of arm's length transfer price
methodologies. These kinds of methodologies are used extensively
across many international jurisdictions in relation to petroleum
and other transfer pricing issues.

Source: Explanatory Statement - Select Legislative Instrument
2005 No. 329 (the Explanatory Statement).
8. The cost plus price is the minimum price at which the
upstream stage of an integrated GTL operation would sell its gas
to the downstream stage in order to cover its upstream costs,
taking into account a proper allocation for its capital costs.
The netback price is the maximum price the downstream stage of
the integrated GTL operation would pay the upstream stage for
sales gas, given the price obtained for or the value of project
liquid produced, in order to cover its costs including a proper
allocation of capital invested. The difference between these
prices identifies the residual profit for a project. The RPM
price, for the purposes of the PRRTAA, is determined by
allocating 50% of the residual profit to the upstream stage and
50% of the residual profit to the downstream stage. However,
where the overall integrated GTL operation incurs an economic
loss because the upstream and downstream costs can't be covered
(in other words, where the netback price is lower than the cost
plus price), the entire loss is attributed to the upstream stage
and diminishes the assessable receipts for the sales gas (the
RPM price is taken to be the netback price). That is, the
liability of the taxpayer to pay PRRT is reduced/eliminated so
far as the operation incurs an economic loss (Regulation Impact
Statement to the Explanatory Statement).
9. The policy objective of the PRRTA Regulations is to provide a
framework to determine the amount of the RPM price, including
identifying and allocating those costs and how far they are to
be taken into account for the upstream and downstream stages.
The PRRTA Regulations provide a mechanism for determining
assessable receipts for project sales gas that becomes an
excluded commodity either through a non-arm's length sale or by
being moved for further processing. The PRRTA Regulations do not
apply to determine whether expenses that are incurred qualify as
deductible expenditure (pursuant to Division 3 of the PRRTAA)
for the purpose of ascertaining a taxpayer's taxable profit in
relation to a petroleum project: there may be deductible
expenditure that is not a relevant cost under the PRRTA
Regulations, and there may be a relevant cost under the PRRTA
Regulations that is not deductible expenditure under the PRRTAA.
Neither do the PRRTA Regulations apply to determine whether an
expense qualifies for deduction for the purpose of determining
the taxable income of a project participant for income tax
purposes: there may be income tax deductions for amounts that
are not relevant costs under the PRRTA Regulations, and there
may be relevant costs under the PRRTA Regulations that do not
give rise to income tax deductions.
10. The RPM price provides a safe harbour by using an arm's
length methodology to work out a gas transfer price. It is an
economic pricing model. Therefore, unlike the PRRTAA, it makes a
clear distinction between capital and revenue costs and
allocates capital costs for each year of tax by using a formula.
It also allocates costs for each year of tax between project
product of the integrated GTL operation and other hydrocarbons.
As it is a simplified pricing model, the steps in the
calculation of an RPM price do not always follow accounting
concepts, standards or records.
11. Measurement of the relevant volume of project sales gas (VG)
is an important step in calculating the assessable receipts of a
taxpayer. The term VG is used in regulations 16 and 17 of the
PRRTA Regulations.
Ruling
Measurement of the volume of project sales gas for the
purposes of regulations 16 and 17
12. Regulations 16 and 17 of the PRRTA Regulations define VG as
the volume of project sales gas to which a relevant pricing rule
applies. As the regulations apply to a particular taxpayer, they
apply the relevant calculations of assessable receipts under the
PRRTAA only to the relevant part of that taxpayer's share of the
project sales gas. That is, the taxpayer's share of the total
volume of project sales gas that is produced in the upstream
stage of the integrated GTL operation in a year of tax and which
enters the downstream stage of the operation for further
processing (or which is sold at that or an earlier point). This
gas is project sales gas whether it then becomes project liquid
(by liquefaction in the integrated GTL operation) or is returned
to and used up (for example as fuel) in the upstream or used up
(for example as fuel or as refrigerant) in the downstream stage
of the operation.
13. As sales gas in an integrated GTL operation for which
assessable receipts must be calculated is the feedstock for
conversion to liquefied product or products, it must have been
fully processed to be suitable for that use ('sales gas',
section 2 of the PRRTAA). Therefore, in an integrated GTL
operation there is no practical difference between the point at
which assessable receipts must be calculated because the sales
gas is moved on for further processing and any earlier point at
which the sales gas could be sold as such.
14. The act of moving on the project sales gas for further
processing triggers the need to calculate assessable petroleum
receipts for it if there is no earlier sale. An actual
integrated GTL operation may produce project sales gas at, and
move it on for further processing from, more than one physical
point. If this is the case, each of the points where project
sales gas is so produced will represent the end of the upstream
stage and the start of the downstream stage (and each will be
the point where assessable receipts must be determined, the PRRT
taxing point commonly known as the PRRT ring fence). The
taxpayer's share of the sum of the volumes of project sales gas
produced at all such points constitutes the total volume of
their project sales gas to which an applicable pricing rule
under regulations 16 and 17 of the PRRTA Regulations may apply.
Each pricing rule applies only to so much of the taxpayer's
share of project sales gas as it can apply to, with the RPM
price being the default rule.
15. The volume of project sales gas (VPSG) for the purposes of
regulations 22 and 23 of the PRRTA Regulations is not limited to
the taxpayer's share of project sales gas. VPSG is the total
volume of project sales gas that is produced in the upstream
stage of the integrated GTL operation in a year of tax,
including the shares of all taxpayers who are participants in
that operation. This is because the cost-plus price under
regulation 22 allocates total upstream costs of all participants
for a year of tax proportionately to all project sales gas of
that year, and the netback price under regulation 23 allocates
total downstream costs of all participants for a year of tax
proportionately to all project sales gas of that year. This is
not true of VPGPREV under regulation 40 of the PRRTA
Regulations, where the instalment RPM is based on the total
volume of project sales gas in the previous year for the
predecessor participant, or participants, whose interest in the
operation was transferred from the predecessor participants.
Otherwise instalment RPM under regulations 39 and 40 of the
PRRTA Regulations is based only on the taxpayer's own share of
the total volume of project sales gas, for the current or for
the previous year of tax. VTDG, as defined in regulation 23, is
the volume of the taxpayer's share of the downstream gas. The
principles discussed in the above paragraphs in relation to VG
are also relevant to the volumes of project sales gas defined as
VPSG, VPGPREV, VPG (as defined in regulation 40) and VTDG.
16. In applying energy coefficients to costs of a phase, so as
to work out the proportion of those costs that represent costs
of producing and processing project sales gas, the energy
content of the total phase hydrocarbons (the energy content of
project product in the numerator and the energy content of all
petroleum in the denominator) is used for the purposes of
regulation 37 of the PRRTA Regulations. This is regardless of
which participants have interests in them, and not just based on
the taxpayer's share of the phase hydrocarbons or of the project
product in that phase.
Apportionment of costs between project product and other
petroleum commodities
17. The apportionment of costs between project product of the
integrated GTL operation and total petroleum including any other
petroleum is relevant to the calculation of an RPM Price. Costs
for any year are apportioned for applicable phases, found by
dividing an integrated GTL operation into distinct phases
separated by phase points.
18. The point where the upstream stage ends and the downstream
stage starts is always a phase point, whether or not there is a
change in the ratio of project product to total petroleum
flowing through the operation before and after the point (sub-subregulation
6(1)(a) of the PRRTA Regulations). This is because upstream
costs applicable to the cost-plus calculation must be separated
from downstream costs applicable to the netback calculation.
Where there is more than one physical point where the upstream
stage ends and the downstream stage starts (refer to paragraph
14 of this Ruling), each such physical point will be a phase
point. These are the physical points where assessable petroleum
receipts for sales gas arise for PRRT purposes.
19. Any other point in the integrated GTL operation where the
ratio of project product to total product (measured by energy
content) changes, is a phase point (sub-subregulation 6(1)(b) of
the PRRTA Regulations). These phase points where there is a
change in the ratio of project product to total petroleum must
be identified, because costs of operations between phase points
will be apportioned according to the constant ratio of project
product to total petroleum applicable between those points. It
is possible for the quantum of flow or the energy content to
change at a point without affecting the ratio of project product
to total product (for example, because petroleum is taken as
fuel proportionately from all petroleum components in a phase).
There will not be a phase point where the quantum of flow (or of
the total energy content) changes, but the ratio of project
product to total product does not change (the Explanatory
Statement, explanation for regulation 6 of the PRRTA
Regulations).
20. The use of petroleum as fuel or as refrigerant in the
upstream stage or the downstream stage of the integrated GTL
operation is use for the purposes of the operation (regulation
4, subregulation 23(1) and regulation 40 of the PRRTA
Regulations). If at a particular point an activity, such as
taking petroleum for fuel, refrigerant or venting of gas, takes
petroleum proportionately from all the petroleum products in the
phase, no phase point will be created.
21. When there is multiple use of a phase is explained by
regulation 7 of the PRRTA Regulations. The actual apportionment
of costs of a phase between project product and other petroleum
is made by applying the formula in regulation 37 of the PRRTA
Regulations.
22. The energy coefficient of a phase for a year of tax, as
defined in regulation 37 of the PRRTA Regulations, is the ratio
of the energy content of project product to the energy content
of all of the petroleum, according to what enters the phase
during the year of tax.
23. A cost incurred in complying with the regulatory requirement
imposed by a public authority (for example, the cost of removing
mercury or carbon dioxide from natural gas) will be a direct
cost if it relates only to one or more phases in the upstream
stage or only to one or more phases in the downstream stage (subregulation
28(3) of the PRRTA Regulations). If the cost relates to both the
upstream stage and the downstream stage it is either apportioned
between direct costs of the upstream stage and the downstream
stage (if it can be reasonably apportioned and exceeds the
threshold (subregulation 28(4) of the PRRTA Regulations)); or it
is treated as an indirect cost if it does not exceed the
threshold, or if it cannot be reasonably apportioned between
direct costs of the upstream stage and the downstream stage (subregulation
28(5) of the PRRTA Regulations).
24. Where an item of plant ceases to be used in the integrated
GTL operation, the original cost of the item no longer forms
part of the RPM price calculation (the Explanatory Statement,
explanation for regulation 36 of the PRRTA Regulations). Any
sale proceeds for such an item do not form part of the RPM price
calculation process. This does not affect any assessable
receipts that arise otherwise than under the RPM process. The
sale proceeds may be assessable receipts under a provision of
the PRRTAA (for example, section 27 of the PRRTAA).
Allocation of capital costs
25. An annual allocation for each capital cost of an integrated
GTL operation, as defined in regulation 31 of the PRRTA
Regulations, is made in each year of tax during the expected
life of the unit of property to which the cost relates (for
costs incurred for a depreciating asset as defined in section
40-30 of the Income
Tax Assessment Act 1997 (ITAA
1997)), or over the expected operating life of the integrated
GTL operation (for costs which are treated as capital costs only
because they were incurred before the production date of the
integrated GTL operation) (subregulations 36(2) and 36(7) of the
PRRTA Regulations). The allocation of capital costs relates to
the effective life or operating life over which returns for the
particular cost must be recovered. When calculating the
cost-plus price and netback price, the allocated amount of
capital costs is adjusted by a volume coefficient to take into
consideration the fluctuations in the volume of project natural
gas recovered from the project from year to year (regulations 22
and 23 of the PRRTA Regulations). The volume coefficient is the
ratio of the volumes of project natural gas processed in the
integrated GTL operation in the current year of tax (VA) to the
estimated average annual volume of project natural gas or the
average volume of project natural gas processed in the previous
years of operation (VB) (regulation 10 of the PRRTA
Regulations).
26. Project natural gas of an integrated GTL operation is
defined in subregulation 4(2) of the PRRTA Regulations as the
petroleum (natural gas) recovered from the project from which
sales gas will be produced and processed into project liquid. In
a typical integrated GTL operation, the project natural gas
recovered in gaseous form from a petroleum project is included
in the measurement of VA. In addition, any project natural gas
that is recovered from the liquid petroleum extracted from the
project is also included in the measurement of VA (refer to
paragraphs 88 and 89 of this Ruling).
27. A reasonable estimation of VNG, the total volume of project
natural gas to be recovered during the life of the operation, as
defined in regulation 9 of the PRRTA Regulations, must be made
on the basis of all the relevant information available to the
taxpayer. The Commissioner must be given estimates by the
participants in an integrated GTL operation of VNG in the year
of tax before the first production year, and if this estimate
changes when new information becomes available, the Commissioner
must be informed of the new estimate for VNG. VNG is not the
same as the expected optimum level of annual production times
the number of years in the operating life of the operation. It
arrives at estimated average annual volume of project natural
gas from the total volume estimated to be produced over the life
of the project and the estimated life of the project, rather
than the other way round.
Measurement of gas and liquid volumes
28. Measurement of gas and liquid volumes is relevant to the
measurement of VG, VA and the calculation of an RPM Price.
29. The Commissioner can approve the use of any particular unit
of measurement for the measurement of gas and liquid volumes.
Such measurements are used to ascertain several ratios for
different purposes. The purposes of the PRRTAA and the PRRTA
Regulations would be frustrated if inconsistent units of
measurement were used for different measurements that need to be
compared with each other. The Commissioner would only approve
the use of a particular unit when the same unit of measurement
is used consistently to measure volumes throughout the
operation, or where different units that are used are compatible
and are converted into a common measurement for the purposes of
any comparisons or ratios between measurements.
30. Project product includes project natural gas of the
integrated GTL operation (from which sales gas will be produced
and processed into liquefied product within the operation),
project sales gas (produced from project natural gas and which
will be processed into liquefied product within the operation)
and all liquefied products derived from project sales gas (for
example, LNG, liquefied ethane, liquefied propane and liquefied
butane) (regulation 4 of the PRRTA Regulations). Any natural
gas, sales gas or project liquid that is used as
fuel/refrigerant or vented/flared in the production of project
sales gas and its processing into project liquid in the
integrated GTL operation is project product (subregulations 4(2)
and 4(3)).
31. For the purposes of regulation 23 of the PRRTA Regulations,
PLVal is the total market value of project liquid produced in a
year of tax. PLVal is calculated by adjusting the sale proceeds
for the project liquid for a year of tax by the market value of
the change in the quantity of project liquid in storage tanks.
As there can be a number of products that constitute project
liquid, the sale proceeds and market value of the change in
quantity in storage tanks of all such products produced in the
integrated GTL operation during a year of tax must be added.
32. The above principle is also relevant in determining PLVal
and PLValprev as defined in regulations 39 and 40 of the PRRTA
Regulations (calculating assessable receipts for the purposes of
ascertaining current period liability in the instalment
provisions of the PRRTAA).
Examples
Measurement of the volume of project sales gas for the
purposes of regulation 17 of the PRRTA Regulations
Example 1
33. In an integrated GTL operation that is owned by a single
taxpayer and processes no external petroleum, the bulk of sales
gas is produced at the end of the 'Pre-cooling for liquefaction'
stage. Some sales gas is recovered by heating the liquid stream
separated at the end of 'Pre-cooling for liquefaction' stage.
Since sales gas is produced at more than one point, each point
where sales gas is produced is a phase point and represents the
PRRT ring fence for calculating the assessable petroleum
receipts for the sales gas produced at that point. The owner of
the operation is entitled to all of the project sales gas
produced in the operation. If all of the sales gas is processed
into project liquid, VG is determined by measuring the volume of
sales gas produced at the two points and then adding them
together.
Apportionment of costs between project product and other
petroleum commodities of the petroleum project
Example 2
34. In an integrated GTL operation that is owned by a single
taxpayer and processes no external petroleum, some of the sales
gas is used to produce electricity. The remaining sales gas is
processed into project liquid. In the relevant year of tax 840
(volume) units of sales gas containing 560 energy units were
produced in the operation. The evaporation of project liquid
produced another 15 units of gas containing 10 energy units. The
gas produced by the evaporation of project liquid was used as
fuel in the upstream stage. If 90 (volume) units of sales gas
containing 60 energy units were used to produce electricity and
only 60% of the electricity produced by the sales gas is used in
the integrated GTL operation, what is the value of VG?
35. The 15 (volume) units of gas produced by the evaporation of
project liquid do not reduce the measurement of project sales
gas. 750 (volume) units of sales gas were processed into project
liquid. This volume is included in the volume of project sales
gas. Of the 90 (volume) units of sales gas used to generate
electricity, 60% is used in the integrated GTL operation.
Therefore, 54 (volume) units meet the definition of project
sales gas. The owner of the operation is entitled to all of the
project sales gas produced in the operation. Therefore, VG is
the sum of these two volumes and it equals 804 (volume) units.
Apportionment of costs between project product and other
petroleum commodities of the petroleum project
Example 3
36. In a typical integrated GTL operation the liquid stream
separated at the exit of the slugcatcher during a year of tax
contained 2,500 units of energy. The project natural gas that
was recovered from this liquid stream contained 225 units of
energy. The stabilised condensate produced from the liquid
stream accounted for the remaining 2,275 energy units. The
operating cost of the phase (recovery of gas from the liquid
stream) for the year was $120,000. The energy coefficient of the
phase in which gas is recovered from the liquid stream is
225/2500 or 0.09. Therefore, an amount of $10,800 ($120,000 *
0.09) will be included on account of the operating cost of this
phase in step 12 of the RPM (regulations 25 and 37 of the PRRTA
Regulations). This amount would then form part of the overall
upstream operating costs (UOC) for the purpose of calculating
the cost-plus price in accordance with regulation 22 of the
PRRTA Regulations.
Apportionment of costs between project product and other
petroleum commodities
Example 4
37. A typical integrated GTL operation may process petroleum
from a producer's own project as well as petroleum from a
petroleum project that belongs to a third party. Petroleum
belonging to the third party may practically enter the plant at
the end of the 'Recovery of petroleum' stage. In the relevant
year of tax natural gas containing 600 energy units from the
producer's own project was processed into 360 (volume) units of
sales gas containing 240 energy units. Natural gas containing
200 energy units from the third party's project was processed
into 90 (volume) units of sales gas containing 60 energy units.
Project natural gas is that volume of natural gas which is
recovered from its own project. Project sales gas is 360
(volume) units containing 240 energy units. Natural gas from
third party's petroleum project, 90 (volume) units of sales gas
containing 60 energy units (produced from the natural gas from
the external project), liquefied product produced from this
sales gas and all of the condensate produced in the operation
would not be project product. Costs of each phase will be
apportioned between project product and other MPCs by taking
into consideration the energy content of project product and the
energy content of all the petroleum that entered the phase in
the assessment year.
Identification of upstream and downstream costs
Example 5
38. Owners of an integrated GTL operation may incur a cost in
removing carbon dioxide and other impurities from project
natural gas. In a typical integrated GTL operation, the cost of
removing impurities is incurred in the 'Removal of impurities'
stage (in the upstream stage). Therefore it is a direct cost.
The cost of insurance of the integrated GTL operation relates to
the entire project. Therefore, it must be split into two direct
costs if it exceeds the threshold amount and can be reasonably
attributed between the upstream and the downstream stages. If it
does not exceed the threshold amount, or it cannot be reasonably
attributed, it will be an indirect cost and split into an
upstream cost half and a downstream cost half.
Allocation of capital costs
Example 6
39. A typical integrated GTL operation is expected to operate
for 15 years. The estimated volume units of project natural gas
that it will process are as follows:
|
Year 1 |
Year 2 |
Year 3-13 |
Year 14 |
Year 15 |
|
45 units |
75 units |
80-90 units |
60 units |
40 units |
The number of units processed in any particular year of years
3-13 will depend on the downtime for maintenance. On average 85
volume units will be processed per annum. During the expected 15
years of operation the project will process an expected 1,155
volume units recovered from the petroleum project. For the
purposes of regulation 9 of the PRRTA Regulations, VNG is 1,155
units, N 15 years and the estimated average annual volume of
project natural gas is 77 units. If the actual volume of natural
gas recovered in the first year is 50 units and in the second
year 80 units, the second year of operation will be the base
year. If the taxpayer were to take the optimum level of
production as the estimated average annual volume of project
natural gas, the actual volume of project natural gas in the
second year of operation will not exceed the estimated average
volume and the second year of operation will not be the base
year. This would be incorrect and would result in an incorrect
value for the volume coefficient.
Measurement of gas and liquid volumes - calculation of PLVal
Example 7
40. In a typical integrated GTL operation liquefied ethane,
liquefied propane and liquefied butane that are produced from
the project sales gas are either used as refrigerant/fuel or
mixed with LNG prior to loading on ships. In a year of tax 650
units of LNG (including methane and other project liquid mixed
in it) were sold for $13b. At the start of the year of tax, the
total volume of project liquid in all storage tanks was 16
units. At the end of the year of tax this volume had increased
to 20 units. The market value of the change in the liquid volume
($80m) is added to the sale proceeds of $13b to arrive at a
value of $13.08b for PLVal (for the purposes of regulation 23 of
the PRRTA Regulations).
Measurement of gas and liquid volumes - LPG gases
Example 8
41. In a typical integrated GTL operation butane and propane are
sold as LPG gases. The sale proceeds for LPG are included in
PLVal. If LPG gases are mixed in condensate, part of the sale
proceeds of condensate will be included in PLVal. If these gases
are used exclusively as fuel or refrigerant, they would not be
included into the calculation of PLVal even though they are
project product.
Measurement of gas and liquid volumes - use of Standard Cubic
Metres
Example 9
42. A question has been raised whether a taxpayer can use the
standard cubic meters as defined in the International System of
Units as a unit of measurement for gas and liquid volumes in an
integrated GTL operation. If the same unit of measurement will
be used consistently to measure gas and liquid volumes
throughout the operation, the Commissioner is not precluded by
the purpose of the PRRTA Regulations from approving the use of
standard cubic meters to measure gas and liquid volumes.
Date of effect
43. This Ruling applies to years of income commencing both
before and after its date of issue. However, this Ruling will
not apply to taxpayers to the extent that it conflicts with the
terms of a settlement of a dispute agreed to before the date of
issue of this Ruling (see paragraphs 75 and 76 of Taxation
Ruling TR 2006/10).
Commissioner of Taxation
17 December 2008
Appendix 1 - Explanation
|
This
Appendix is provided as information to help you
understand how the Commissioner's preliminary view has
been reached. It does not form part of the proposed
binding public ruling. |
The processes in an integrated GTL operation
44. A simplified diagram showing the main possible processing
stages and the flows of petroleum possible in a typical
integrated GTL operation is included after paragraph 46 of this
Ruling. The diagram is used for illustration purposes only and
the processes in an actual integrated GTL operation, and the
sequence of processes and the flows of petroleum in an actual
operation, will depend on the particular circumstances of that
integrated GTL operation.
45. 'Petroleum' for the purposes of the PRRTAA has the same
meaning as under the extended definition of that term in the Offshore
Petroleum Act 2006 ,
which by section 6 of that Act means:
-
(a)
-
any naturally occurring hydrocarbon,
whether in a gaseous, liquid or solid state;
-
(b)
-
any naturally occurring mixture of
hydrocarbons, whether in a gaseous, liquid or solid
state; or
-
(c)
-
any naturally occurring mixture of:
-
(i)
-
one or more hydrocarbons, whether
in a gaseous, liquid or solid state; and
-
(ii)
-
one or more of the following, that
is to say, hydrogen sulphide, nitrogen, helium
and carbon dioxide;
-
-
and:
-
(d)
-
includes any petroleum as defined by
paragraph (a), (b) or (c) that has been returned to a
natural reservoir; ...
(the above is an extract of the definition of petroleum in
section 6)
Petroleum is intended to mean what is recovered, including a
range of things that are not hydrocarbons, and will ordinarily
be recovered mixed with other things which are not petroleum
(which may include, for instance, mercury and water). It
includes gaseous, liquid and solid hydrocarbons and mixtures
that are gases, liquids and solids.
46. The first stage of the illustrated operation starts with the
recovery of petroleum from wellheads belonging to the petroleum
project. (Every petroleum project includes the operations and
facilities for the recovery of petroleum from the production
licence areas for the project.) A mixture of liquid and gaseous
petroleum with a range of non-hydrocarbon components both
included in 'petroleum' as defined and other components is
recovered, transported, treated and separated into a mixture
forming a liquid stream and a mixture forming a gas stream
(point A in the diagram). That separation, commonly by a 'slug
catcher', is likely in practice to be carried out at the point
where the recovered stream is first brought ashore. At the end
of the first stage separation, the main constituent in the gas
stream is likely to be methane, whereas pentane and hexane are
ordinarily the main constituents in the liquid stream.

47. Impurities, or non-hydrocarbon components, such as carbon
dioxide, hydrogen sulphide, water, mercury and nitrogen in the
gas stream are removed in the second stage of the operation as
illustrated (point A to point C in the diagram). In the third
stage of the operation illustrated (point C to point D in the
diagram), the temperature of the gas stream is gradually lowered
until any remaining pentane and heavier hydrocarbons are
liquefied and separated. At the end of the third stage (point D
in the diagram) the gas stream should meet the definition of
sales gas (the definition of sales gas has been explained at
paragraph 55 of this Ruling).
48. In the fourth and final stage (point D to point H in the
diagram), sales gas is further cooled in a liquefaction train
which results in liquefaction of sales gas into its separate
constituents (or, depending on the particular project, a
combination of some of them), namely, butane, propane, ethane
and methane. Storage of liquefied gases (whether individually or
in some combination) and their loading on ships is treated as
part of this stage for the purposes of applying the RPM
methodology under the PRRTA Regulations. Methane is the main
constituent of liquefied natural gas (LNG). LNG may also contain
small quantities of liquefied ethane, liquefied propane or
liquefied butane, increasing the thermal value of the LNG, which
may be desirable to meet buyer specifications or may be
practically convenient in a particular integrated GTL operation.
Ethane, propane and butane may each also be sold individually
and may be used as refrigerant in the integrated GTL operation.
LPG is a mixture of liquefied butane and liquefied propane.
49. As shown in the diagram, the four broad stages of a typical
integrated GTL operation can be referred to as:
-
(a)
-
the recovery of petroleum stage;
-
(b)
-
the removal of impurities stage;
-
(c)
-
the pre-cooling for liquefaction stage;
and
-
(d)
-
the liquefaction stage.
50. The first three stages collectively form the upstream stage
while the liquefaction stage is part of the downstream stage of
the operation, also including storage of liquefied gases and
their loading on ships. These stages of an integrated GTL
operation need not correspond to the phases of the operation for
the purposes of applying the RPM methodology under the PRRTA
Regulations, other than the phase ending at the end of the
upstream stage and the phase beginning at the start of the
downstream stage. A single stage could consist of a number of
phases and a phase may cover more than one stage of the
operation.
51. The liquid petroleum stream separated in the 'Recovery of
petroleum' stage or (less commonly) in the 'Pre-cooling for
liquefaction' stage may contain some lighter hydrocarbons (for
example, propane and butane). The lighter hydrocarbons will
usually be separated from the liquid stream and may rejoin the
mainstream gas flow or may be used as fuel in the integrated GTL
operation. If this is the case, for costing purposes, the
processing of the liquid stream up to the point where light
gases are separated will be to some degree part of the
integrated GTL operation in applying the RPM methodology, and
will be a phase for that purpose, costs being apportioned
according to the ratio of energy in the light gases to the
energy in all the hydrocarbons in the whole liquid processing
stream (see paragraphs 72 to 79 of this Ruling). Where this is
not the case, the liquid stream separated at the end of either
stage would have left the integrated GTL operation (for sale or
for further processing), because it would no longer have any
component of project product for the purposes of the RPM
methodology and so no part of the costs from that point at which
the liquid stream left the integrated GTL operation would be
relevant to the calculation of the RPM price of sales gas under
the PRRTA Regulations. Costs incurred in the further processing
of the liquid petroleum cannot be included in the costs of the
integrated GTL operation. The liquid petroleum leaving an
integrated GTL operation will usually meet the definition of
condensate in section 2 of the PRRTAA but will leave the
integrated GTL operation, in applying the RPM methodology,
whether the liquid is condensate or not. The application of the
PRRTAA in relation to the liquid or to marketable petroleum
products first derived from it is not affected by the operation
of the RPM methodology.
52. Natural gas or sales gas from an external project may enter
an integrated GTL operation for processing at any stage of the
operation. The operation as illustrated includes this. For
example, part of the natural gas stream from another petroleum
project may enter a typical integrated GTL operation at point B
in the diagram, immediately after the start of 'Removal of
impurities' stage. Similarly, sales gas from another petroleum
project may enter the operation at point E in the diagram,
immediately after the start of 'Liquefaction' stage. Natural gas
or sales gas from the project can also be taken out of the
integrated GTL operation for non-project purposes (and so to
that extent would not be part of the project product of the
integrated GTL operation). In a typical operation sales gas may
be taken from point F in the diagram, a point close to the start
of the 'Liquefaction' stage. Natural gas, sales gas or liquefied
product may also be taken for use as fuel or refrigerant in the
overall operation, for example, from points C or H in the
diagram.
53. Liquefied product that evaporates from storage tanks may be
used as fuel in the integrated GTL operation. Liquefied ethane,
liquefied propane and liquefied butane may be marketed
separately or mixed with LNG or other products. Liquefied
propane and liquefied butane may be mixed and marketed as LPG.
Some relevant definitions
54. As the PRRTA Regulations are made under the PRRTAA, terms
used in those Regulations have the meanings specified in that
Act unless some specific meaning is given for the purpose of
those Regulations. So, for instance, petroleum is not specially
defined for the purposes of those Regulations but is defined by
section 2 of the PRRTAA to have the same meaning as in the Offshore
Petroleum Act 2006 .
As outlined in paragraph 45 of this Ruling, petroleum is defined
in the Offshore
Petroleum Act 2006 as
a substance consisting of one or more naturally occurring
hydrocarbons in gaseous, liquid or solid form and may include
impurities such as hydrogen sulphide, nitrogen, helium and
carbon dioxide.
55. Sales gas is defined in section 2 of the PRRTAA. Sales gas
means a substance:
-
·
-
which is in a gaseous state when at the
temperature of 15 degrees Celsius and a pressure of one
atmosphere; and
-
·
-
which consists of naturally occurring
hydrocarbons, or a naturally occurring mixture of
hydrocarbons and non-hydrocarbons; and
-
·
-
the principal constituent of which is
methane; and
-
·
-
which, if it is to be used as feedstock
for conversion to another product, has been processed so
that it is suitable for that use; or in any other case,
has been processed so that it is suitable for direct
consumption as energy.
56. The term 'excluded commodity' is defined in section 2 of the
PRRTAA to mean a marketable petroleum commodity that:
-
·
-
has been sold;
-
·
-
after being produced, has been further
processed or treated;
-
·
-
has been moved away from the place of its
production other than to a storage site adjacent to that
place; or
-
·
-
has been moved away from a storage site
adjacent to the place of its production.
57. The definition of a 'marketable petroleum commodity' (MPC)
means the following products produced from petroleum:
-
·
-
stabilised crude oil;
-
·
-
sales gas;
-
·
-
condensate;
-
·
-
liquefied petroleum gas (LPG);
-
·
-
ethane; and
-
·
-
any other product declared by regulation
to be an MPC.
However, it does not include products produced from another MPC.
This means that so far as an MPC becomes an excluded commodity,
for example, by being moved away from its place of production or
adjacent storage, it cannot do so again. Therefore there can be
no double counting of assessable receipts for an MPC. Refer to
paragraph 96 of this Ruling for further commentary relating to
LPG produced from project sales gas.
Measurement of the volume of project sales gas for the
purposes of regulations 16 and 17 of the PRRTA Regulations
58. The discussion on VG in the following paragraphs explains
the relevant PRRTA Regulations and how they operate to require
the measurement of project sales gas at relevant points. Each
regulation operates to specify the assessable petroleum receipts
of a particular taxpayer for their share of the project sales
gas of the integrated GTL operation for the year of tax. The
taxpayer's share is a share of the total volume of project sales
gas that is produced in the upstream stage of the integrated GTL
operation in the year of tax; which is not sold at arm's length;
and which enters the downstream stage of the operation for
further processing (or which is sold at that or an earlier
point). The regulations apply only to the taxpayer's share of
project sales gas, and only if the taxpayer is a participant in
the integrated GTL operation (subregulations 14(2) and 15(2) of
the PRRTA Regulations). Otherwise, assessable receipts are
worked out as if the sales gas were any other MPC, that is, on
the basis of the general provisions of the PRRTAA without the
benefit of the specific rules and methodologies of the PRRTA
Regulations. A taxpayer is a participant in the integrated GTL
operation if they hold an interest in the operation that
entitles them to petroleum product of the operation at the end
of at least one phase of the operation (regulation 8 of the
PRRTA Regulations). Therefore, any taxpayer who is entitled to
project sales gas at the end of the upstream stage is a
participant in the operation, as the end of the upstream stage
and start of the downstream stage is a phase point and the end
of a phase (sub-subregulation 6(1)(a) of the PRRTA Regulations,
and see the discussion of phase points at paragraphs 72 to 79 of
this Ruling).
59. Project sales gas of an integrated GTL operation is the
sales gas produced from the project natural gas of the operation
and which will be processed into liquefied product in the
operation, or used in doing so (subregulation 4(3) of the PRRTA
Regulations). So project sales gas includes what becomes
liquefied product as well as any sales gas that is returned to
and used up (say as fuel) in the upstream stage or used up (say
as fuel or as refrigerant) in the downstream stage of the
integrated GTL operation. The act of moving on the project sales
gas for further processing triggers the need to calculate
assessable petroleum receipts if there is no earlier sale
('excluded commodity' paragraph (c), section 2 of the PRRTAA;
such movement necessarily precedes or is simultaneous with the
further processing or treatment which would also trigger
calculation under 'excluded commodity' paragraph (b)). As
project sales gas of an integrated GTL operation is the
feedstock for conversion to liquefied product or products, it
must have been fully processed to be suitable for that use
('sales gas', section 2 of the PRRTAA). The point at which that
processing is completed is a matter of fact, and in practice is
the point at which the gas is ready to enter the processing by
which liquefied product or products are produced from it.
Therefore, any non-arm's-length sale making the project sales
gas an excluded commodity with a determination of assessable
receipts to which regulation 16 of the PRRTA Regulations applies
and any later movement for further processing making the sales
gas an excluded commodity with a determination of assessable
receipts to which regulation 17 of the PRRTA Regulations applies
will happen in practice at much the same point. The volume
calculation for either regulation will be at practically the
same point and no significant disparity between the measurements
for either regulation is likely to arise in practice.
60. The volume of project sales gas for which assessable
receipts are to be calculated, VG, is defined in regulations 16
and 17 of the PRRTA Regulations as the volume of project sales
gas of the taxpayer that is sold other than at arm's length in
the assessment year or that becomes an excluded commodity in the
assessment year without being sold. A transaction, the volume of
gas subject to which is VG under regulation 17, is defined in
regulation 17 as the act by which sales gas becomes or became an
excluded commodity. Therefore, whether regulation 16 or
regulation 17 applies, the relevant point for calculating the
assessable receipts is the point at which the taxpayer's share
of project sales gas becomes an excluded commodity under section
2 of the PRRTAA.
61. Methane (CH4) is the main constituent of sales gas. Ethane
(C2H6), propane (C3H8), and butane (C4H10) are also in a gaseous
state at a temperature of 15 degrees Celsius and a pressure of
one atmosphere (refer to paragraph 55 of this Ruling or section
2 of the PRRTAA for the definition of sales gas). These
hydrocarbons can readily be part of a sales gas substance.
Pentane (C5H12), hexane (C6H14) and other heavier hydrocarbons
are not themselves in gaseous state at a temperature of 15
degrees Celsius and a pressure of one atmosphere. Typically, in
an integrated GTL operation, pentane and heavier hydrocarbons
must be removed from the gaseous mixture before it can meet the
definition of sales gas, because if they are included the
mixture is not suitable to be used as feedstock for conversion
to a liquefied product. Water, carbon dioxide, hydrogen sulphide
and mercury, like the heavier hydrocarbons, can cause problems
with the operation of a liquefaction train if they are included
in a gaseous feedstock mixture. In a typical integrated GTL
operation, until all the heavier hydrocarbons and these
impurities have been removed, the gaseous mixture will not meet
the definition of sales gas because it would not yet have been
processed to be suitable for liquefaction in that operation.
However, in any particular integrated GTL operation, if a
substance containing some pentane or heavier hydrocarbons or
other inclusions meets all of the conditions contained in the
definition of project sales gas which includes the condition
that it be suitable to be used as feedstock for conversion to a
liquefied product, then the substance will meet the definition
of project sales gas for that particular integrated GTL
operation. Refer to Alternative
view 1 at
paragraph 101 of this Ruling for an alternative view. The end of
stage three (Pre-cooling for liquefaction) in the diagram after
paragraph 46 of this Ruling is the point (point D) where the
bulk of sales gas will be produced in an integrated GTL
operation as a matter of practice. However, there may be more
than one physical point in a particular integrated GTL operation
at which project sales gas becomes an excluded commodity, and
each of those points will be the end of the upstream stage and
the start of the downstream stage (and the point where
assessable receipts must be determined, the PRRT taxing point,
commonly known as the PRRT ring fence). The taxpayer's share of
the sum of the volumes of project sales gas becoming excluded
commodities at all such points constitutes the total volume of
their project sales gas to which the pricing rules under
regulations 16 and 17 of the PRRTA Regulations may apply. Each
pricing rule applies only to so much of the taxpayer's share of
project sales gas as becomes an excluded commodity in the
relevant way, for regulation 16 by being sold other than at
arm's length, for regulation 17 other than by being sold. The
rules cannot overlap because once any part of the project sales
gas has become an excluded commodity it remains so and because
what is produced from a marketable petroleum commodity is for
that reason not a marketable petroleum commodity itself.
62. The definition of 'excluded commodity' (refer to paragraph
56 of this Ruling or section 2 of the PRRTAA) refers to moving
of an MPC to or from a storage site adjacent to its place of
production. What is a storage site adjacent to the place of
production of an MPC has not been defined in the PRRT
legislation and is a question of fact. The distance from the
place of production as well as the intention of the taxpayer are
relevant in determining whether an MPC is being stored at a
place adjacent to its place of production. Storage at a site
even a kilometre away from the place of production of an MPC may
qualify as adjacent storage if the intention of the taxpayer is
to store the MPC until it is sold. On the other hand, moving
sales gas produced in an integrated GTL operation through a
pipeline even by a centimetre into the next stage for further
processing is movement away from the place of production of the
sales gas other than to adjacent storage, because the sales gas
so moved is not intended to be stored, and causes the sales gas
to become an excluded commodity. An MPC that has been moved to a
storage site adjacent to the place of its production will become
an excluded commodity even when there is no change in its
location, if it is sold or is further processed or treated
('excluded commodity', section 2 of the PRRTAA).
63. The upstream stage and the downstream stage of an integrated
GTL operation have been defined in regulation 5 of the PRRTA
Regulations. The upstream stage will normally end at the point
when an assessable receipt arises, that is, when natural gas
recovered from the project is converted into sales gas (an MPC)
and that sales gas is moved on for further processing (or sold,
in practice necessarily at the same point as discussed at
paragraph 59 of this Ruling). Transportation and further
processing of sales gas into liquefied product take place in the
downstream stage. The assessable petroleum receipts of a
taxpayer from the sales gas produced in an integrated GTL
operation are calculated at the point separating the two stages
(the PRRT ring fence) by applying regulations 16 and 17 of the
PRRTA Regulations. Where those provisions apply the RPM price to
the relevant gas volume, that price is specified by regulations
20 and 21 of the PRRTA Regulations. Where there is sufficient
information and there is no advance pricing arrangement or CUP
(comparable uncontrolled price) applicable, the RPM price worked
out in accordance with regulation 20 is the average of the
cost-plus price under regulation 22 and the netback price under
regulation 23 of the PRRTA Regulations, with the RPM method and
its necessary information further specified by Part 5 of the
PRRTA Regulations.
64. The liquid stream separated at the end of 'Recovery of
petroleum' stage may have natural gas dissolved in it in
practice. Similarly, the liquid stream separated at the end of
'Pre-cooling for liquefaction' stage may have constituents of
sales gas dissolved in it. If project sales gas is recovered
from either liquid stream that has been separated from the gas
stream and the recovered gas joins the mainstream flow of sales
gas, the point where gas is recovered from the liquid stream
will also represent the PRRT ring fence. Where sales gas is
produced at more than one point in an integrated GTL operation,
there will be more than one point that represents the PRRT ring
fence (refer to Example 1, paragraph 33 of this Ruling). If the
gas recovered is not yet project sales gas, for instance because
it includes things that have to be removed before it will have
been processed to be suitable as feedstock for the production of
liquefied products, the point at which it is recovered from the
liquid may be a phase point but will not be a point at which
assessable receipts arise.
65. The volume of gas that is recovered from the liquid stream
separated at the end of the 'Pre-cooling for liquefaction' stage
is produced from natural gas recovered from the petroleum
project that belongs to the integrated GTL operation (assuming
that only gas recovered from the project is processed in the
operation). In a typical operation this gas will join the
mainstream sales gas to be processed into project liquid within
the operation. If it does not itself meet the definition of
sales gas in section 2 of the PRRTAA, it will still meet the
definition of project natural gas at the point when it is
recovered. When this gas joins the mainstream sales gas (if it
does so), it then becomes part of project sales gas in any case.
The recovered gas does not undergo any change between the point
where it is recovered and the point where it joins the
mainstream sales gas. Therefore, for administrative convenience,
there is no practical reason why it should not be treated as
sales gas from the point of its recovery from the liquid stream.
66. On the other hand, it is possible that liquid petroleum
separated at the end of 'Recovery of petroleum' or 'Pre-cooling
for liquefaction' stage is sold as condensate without recovering
any gases dissolved in it. In that case, the liquid petroleum
will meet the definition of other MPC (not a project product)
produced in an integrated GTL operation and no part of the costs
from that point of separation will form part of the costs of the
integrated GTL operation taken into account in calculating the
RPM price. At the moment that the MPC that is not project
product becomes an excluded commodity, there will be an
assessable petroleum receipt in relation to it pursuant to
section 24 of the PRRTAA.
67. VG is defined for regulation 17 of the PRRTA Regulations as
the volume of project sales gas that becomes an excluded
commodity other than by sale, practically by being moved to
further processing in the integrated GTL operation. It
represents the volume of project sales gas that becomes an
excluded commodity without sale and gives rise to assessable
receipts for the calculation of PRRT payable by a taxpayer.
Therefore, VG is measured at the PRRT ring fence, the point
representing the end of the upstream stage and the start of the
downstream stage. It follows that where a number of points in
the entire operation represent the PRRT ring fence, VG is the
taxpayer's share of the sum of the volumes of project sales gas
measured at all those points (refer to Example 1 at paragraph 33
of this Ruling).
68. The definitions of project natural gas and project sales gas
in regulation 4 of the PRRTA Regulations specifically include
any natural gas or sales gas used in the project (for example,
as fuel or refrigerant in the integrated GTL operation).
Therefore, once the volume of project sales gas has been
measured (upon its being moved into the downstream stage),
taking project sales gas for fuel would not affect the measured
amount of VG.
69. Project liquid is usually stored at very low temperatures in
insulated tanks before it is loaded on ships. It is normal for
some of the project liquid to evaporate and sales gas produced
by the evaporation of project liquid may be used as fuel or
returned as feedstock for liquefaction in the integrated GTL
operation. This sales gas would have been produced from another
MPC, namely, the sales gas that was already included in the
definition of VG. Therefore, sales gas generated from the
evaporation of project liquid and returned as feedstock for
liquefaction will not meet the definition of an MPC when
returned, will not become an excluded commodity at that point
(section 2 of the PRRTAA) and its volume does not have to be
added again to the volume of sales gas measured at the end of
the upstream stage for which assessable receipts arise.
70. The calculation of a cost-plus price in regulation 22 of the
PRRTA Regulations and a netback price in regulation 23 of the
PRRTA Regulations also require measurement of the volume of
project sales gas (VPSG), the volume of project sales gas
produced in the integrated GTL operation in the year of tax.
VPSG is the total volume of project sales gas of the integrated
GTL operation that is produced in the upstream stage in the year
of tax, not just the taxpayer's share of project sales gas. This
is because the cost-plus price under regulation 22 allocates
total upstream costs of all participants for a year of tax
proportionately to all project sales gas of that year, and the
netback price under regulation 23 allocates total downstream
costs of all participants for a year of tax proportionately to
all project sales gas of that year. (This is why participants
need not be entitled to any share of project sales gas at the
taxing point, if they are entitled to any petroleum product of
the operation at the end of any phase, under regulation 8 of the
PRRTA Regulations.) In applying energy coefficients to costs of
a phase, so as to work out the proportion of those costs that
represent costs of producing and processing project sales gas,
the energy content of the total phase hydrocarbons (the energy
content of project product in the numerator and the energy
content of all petroleum in the denominator) is used for the
purposes of regulation 37 of the PRRTA Regulations. This is
regardless of which participants have interests in them, and not
just having regard to the taxpayer's share. However, the
foregoing analysis for volume measured and the point at which it
is measured is otherwise equally relevant to the measurement of
VPSG under regulations 22 and 23. It is also relevant to the
measurement of VTDG, the taxpayer's share of the volume of
project sales gas, as defined in regulation 23. As the energy
content of project sales gas is measured at the end of the
upstream stage, as a phase point, the foregoing analysis of the
volume for which the energy content is measured and the point at
which it is measured is then relevant for the purposes of
regulation 37.
71. PRRT instalments (the notional tax amount) for a participant
in an integrated GTL operation are calculated under Part 6 of
the PRRTA Regulations. The formulae for the calculation of the
notional tax amount of a participant who uses the RPM price for
the calculation of assessable petroleum receipts for sales gas
under regulations 14 or 15 of the PRRTA Regulations require the
measurement of VPGprev, the participant's, or the predecessor
participants', share of project sales gas for the previous year
of tax (depending on whether regulation 39 or regulation 40 of
the PRRTA Regulations applies); or VPG, the participant's share
of project sales gas for the instalment period (regulation 40).
Therefore, the foregoing analysis of the volume measured and the
point at which it is measured for the purposes of regulations 16
and 17 of the PRRTA Regulations also applies to the measurement
of VPGprev and VPG for the purposes of regulations 39 and 40.
Apportionment of costs between project product and other
petroleum commodities
72. An integrated GTL operation will usually produce condensate
and sales gas. Some or all of the sales gas produced is
converted to project liquid. Where some of the natural gas or
sales gas from an integrated GTL operation is used for
non-project purposes (for example, as pipeline gas for a
fertiliser plant or for domestic gas supply) or natural gas or
sales gas from an external project is processed in the
integrated GTL operation, that natural gas (or sales gas) will
not meet the definition of project natural gas (or project sales
gas) and assessable receipts for it will arise as if it was
another MPC and not project sales gas of the integrated GTL
operation. A particular integrated GTL operation may produce
other MPCs that are not part of project liquid produced from
project sales gas. Therefore, the costs (both operating costs
and allocated capital costs) of the operation must be
apportioned for each year between producing project product and
all petroleum or petroleum product recovered, processed or
produced in the operation (adopting the definition of 'petroleum
product', regulation 3 of the PRRTA Regulations, as the
allocation of phase costs is worked out only on the energy
content of project product as a ratio to all petroleum product,
regulation 37 of the PRRTA Regulations). Project product of an
integrated GTL operation consists of:
-
·
-
project natural gas, that is, the gas
stream of the petroleum project from which sales gas
will be produced and processed into liquefied product by
the project or used in doing so;
-
·
-
project sales gas, that is, the sales gas
produced from the project natural gas and which will be
processed into liquefied product by the project or used
in doing so; and
-
·
-
project liquid, the liquefied product
processed from project sales gas (subregulations 4(2),
4(3), 4(4) and 4(5) of the PRRTA Regulations).
Petroleum product of an operation means petroleum or a product
of petroleum that is recovered, produced or processed in the
operation (definition, petroleum
product ,
regulation 3 of the PRRTA Regulations). It is not limited to
marketable petroleum products and their precursors, as it needs
to include all petroleum or products of petroleum in each phase,
both upstream and downstream, even if a marketable petroleum
product has already been produced and is included in the phase.
73. In order to apportion costs and to determine the assessable
receipts for project sales gas produced and processed in the
integrated GTL operation, the whole operation is divided into a
number of phases. The start and the end of each phase are phase
points. The apportionment of costs is done on the basis of the
ratio of energy content of project product to the energy content
of total petroleum or petroleum product flowing through a phase
(regulation 37 of the PRRTA Regulations). The definition of a
phase point means that this ratio is constant throughout a
phase, and so provides a common basis for apportioning all costs
of the phase.
74. The point where the upstream stage ends and the downstream
stage starts is always a phase point (sub-subregulation 6(1)(a)
of the PRRTA Regulations), whether or not the ratio of project
product to total petroleum changes at that point. This is
because upstream costs applicable to the cost-plus calculation
must be separated from downstream costs applicable to the
netback calculation. Assessable receipts of a taxpayer for a
year of tax are determined for the volume of project sales gas
at the end of the upstream stage (regulations 16 and 17 of the
PRRTA Regulations). As discussed in paragraphs 61 and 64 of this
Ruling, there can be more than one physical point in an
integrated GTL operation where sales gas becomes an excluded
commodity and so where the upstream stage ends and the
downstream stage begins. All such physical points will be phase
points and they each represent part of the end of the upstream
stage.
75. A phase point arises at any other point in an integrated GTL
operation where the ratio of project product to total petroleum
('petroleum product') (measured by their energy content, under
regulation 37 of the PRRTA Regulations) flowing through the
operation changes (sub-subregulation 6(1)(b) of the PRRTA
Regulations). The start of the upstream stage is the point where
petroleum is recovered from the project as part of the
integrated GTL operation. At the end of the downstream stage
project liquid of the integrated GTL operation leaves the
operation and no further phases can arise. Therefore, the start
of the upstream stage and the end of the downstream stage are
always practically phase points as explained in the Explanatory
Statement.
76. The location of other phase points depends on the change in
the proportion of project product to total petroleum ('petroleum
product'), measured by their energy contents. A change in the
total volume or total energy content may occur within a phase
and does not necessarily give rise to a phase point. For a phase
point to exist, the ratio of project product to total petroleum
(measured by their energy content) must change (the Explanatory
Statement, explanation to regulation 6 of the PRRTA
Regulations). It is possible for the quantum of flow and the
energy content to change at a point without affecting the ratio
of project product to total product (for example, the flow of
gas may be split into two or more streams for processing in
different liquefaction trains or petroleum may be taken as fuel
proportionately from all petroleum products in a phase). A point
where the quantum of flow (or of the energy content) changes,
but the ratio of project product to total product does not
change, will not be a phase point.
77. The use of petroleum as fuel or as refrigerant in the
upstream stage or the downstream stage of the integrated GTL
operation is use for the purposes of the project (regulation 4,
subregulation 23(1) and regulation 40 of the PRRTA Regulations).
If at a particular point an activity such as taking petroleum
for fuel or venting of gas takes petroleum proportionately from
all the petroleum products in the phase, the ratio of project
product to total product will not change. Therefore, no phase
point will be created as a result of that activity. A volume of
sales gas that is taken from the downstream stage for use as
fuel in the upstream stage is also included in the measurement
of project sales gas. Gas used as fuel in the overall integrated
GTL operation is specifically included in the definitions of
project natural gas, project sales gas (subregulations 4(2) and
4(3)), VTDG (subregulation 23(1)), VPG and VPGprev (subregulations
40(2) and 40(3)) (refer to Example 2, paragraphs 34 and 35 of
this Ruling).
78. The concept of multiple use of a phase is defined in
regulation 7 of the PRRTA Regulations. Each subregulation of
regulation 7 explains the principle that is relevant to
different processes within an integrated GTL operation.
Subregulation 7(1) explains that there is multiple use in a
phase related to recovery when petroleum other than project
natural gas of the integrated GTL project is recovered too.
Subregulation 7(2) explains that there is multiple use in a
phase related to production of project sales gas when marketable
petroleum products other than project sales gas of the
integrated GTL project are produced as well. Subregulation 7(3)
explains that there is multiple use in a phase related to
processing of project sales gas into project liquid when there
is processing into liquid of petroleum that is not also project
sales gas of the integrated GTL project. Subregulation 7(4)
explains that there is multiple use in a phase related to
transportation of project product when petroleum that is not
project product of the integrated GTL project is transported
too. Subregulation 7(5) explains that there is multiple use of a
storage facility when it is used to store petroleum that is not
project product of the integrated GTL project too. Subregulation
7(6) explains that there is multiple use of a loading facility
when it is used to load petroleum that is not project product of
the integrated GTL project too. However, the actual
apportionment of costs between project product and other
petroleum is made by applying the formula in regulation 37 of
the PRRTA Regulations. Irrespective of whichever subregulation
of regulation 7 applies to a phase, and the references there to
units of property in some contexts, the formula for
apportionment of all costs for all the phases remains the same
and applies to all phase costs, not only allocated capital costs
of a phase. Apportionment does not apply to costs which are not
phase costs, such as indirect costs or personal costs
(regulation 37, and see note to subregulation 32(4) of the PRRTA
Regulations). Apportionment also does not apply to the costs
incurred in processing project product. All the included costs
(refer to paragraph 81 of this Ruling) of processing project
natural gas to extract gaseous condensate and other impurities,
whether they are marketable or not, are applied to the
production of project sales gas and are included in the
cost-plus component of the RPM price. All of the included costs
of processing project sales gas to produce project liquid are
applied to the production of project liquid and are included in
calculating the netback component of the RPM price. Refer to
Example 3 at paragraph 36 of this Ruling for an example of
apportionment of costs between project product and other
commodities of the petroleum project and Example 4 at paragraph
37 of this Ruling for an example of apportionment of costs
between project product and other petroleum commodities.
79. The energy coefficient for a phase, as defined in regulation
37 of the PRRTA Regulations, depends on the ratio of the energy
content of project product entering the phase to that of all of
the petroleum product entering the phase (definitions of 'Phase
project energy' and 'Total phase energy' in regulation 37). A
change to the petroleum after it has entered a phase need not
affect the calculation of the energy coefficient. For example,
if sales gas is taken proportionately as fuel for the upstream
stage of the operation from a phase that is in the downstream
stage, the energy coefficient for each phase is not affected.
The following illustrations depict phase points and phases.
Figure 2: The point where the
petroleum recovered in a typical integrated GTL operation is
separated into petroleum (natural gas) and other petroleum is a
phase point (refer to paragraphs 51 and 88 to 90 of this
Ruling).

Figure 3: The point where the
upstream stage ends and the downstream stage starts is always a
phase point (refer to paragraph 74 of this Ruling).

Figure 4: The point during the
processing of project natural gas at which the condensate
mixture is removed constitutes a phase point. (Note that if no
recoverable project natural gas was contained in the condensate
mixture, then there would not be a phase point in relation to
the condensate mixture.)

Figure 5: A phase point arises
where the ratio of project product to total petroleum flowing
through the operation changes, for example, where the integrated
GTL operation processes petroleum from an external project.

Figure 6: A phase point arises
where the ratio of project product to total petroleum flowing
through the operation changes, for example, where natural gas or
sales gas is taken for non-project use.

Figure 7: A phase point arises
where the ratio of project product to total petroleum flowing
through the operation changes.

Figure 8: Where fuel for the
project or venting of gas takes petroleum proportionately from
all petroleum products in a phase, no phase point arises (refer
to paragraph 77 of this Ruling).

80. Regulatory authorities, for example Commonwealth and State
Government departments, may impose conditions on the
participants in an integrated GTL operation in order to change
the impact of the project. Costs are incurred in complying with
the regulatory requirements imposed by Government. A cost of
complying with the regulatory requirements will be a direct cost
so far as it relates to a single phase or can be reasonably
apportioned to a number of phases either solely in the upstream
stage or solely in the downstream stage (regulation 28 of the
PRRTA Regulations). However, this will only be so far as it is a
relevant sector cost, wholly and directly attributable to
production, to transport, to storage, to marketing, or to
selling as part of the integrated GTL operation. For example,
the cost of separating carbon dioxide in the process of removing
impurities from natural gas, or pursuant to a regulatory
requirement, would be a direct cost of the upstream stage of an
integrated GTL operation. However, the cost of sequestering that
carbon dioxide would not be a direct cost of the upstream stage
because it is not an included cost (item (d) of regulation 27
and regulation 30 of the PRRTA Regulations). If a cost relates
to the entire project in a way that is not wholly and directly
attributable to relevant sectors, for example, the cost of
insurance of the integrated GTL operation, it is treated as an
indirect cost. A cost that is attributable both to upstream and
downstream stages will only be divided into two direct costs
(one upstream, one downstream) if it exceeds the threshold
amount specified in subregulation 28(7). Below the threshold, it
is an indirect cost. Indirect costs are divided into two halves,
one attributed to the upstream stage, the other to the
downstream stage (refer to Example 5 at paragraph 38 of this
Ruling).
81. Regulation 25 of the PRRTA Regulations provides details of
the steps required in calculating the RPM. The RPM is a method
to calculate a transfer price for project sales gas which is
used to ascertain the assessable petroleum receipts of a
taxpayer. Step 6 of the RPM requires the taxpayer to identify
the amounts of the relevant included costs. These include
capital costs incurred up to and including the assessment year.
Included costs are defined in regulation 30 of the PRRTA
Regulations. Included costs are costs associated with an
integrated GTL operation that are not specifically excluded by
regulation 27 or regulation 29 of the PRRTA Regulations (costs
relating to exploration, feasibility study, environmental study,
removal of infrastructure, environmental restoration and those
costs which are excluded costs for the purposes of the PRRTAA
other than GST, indirect administrative, accounting and work
costs, and land or building costs for administrative or
accounting activities are specifically excluded, as are the
personal costs of other participants in the integrated GTL
operation).
82. Where an item of plant that was originally acquired for use
in an integrated GTL operation ceases to be used in the
operation, the costs incurred in acquiring that item are no
longer associated with the operation. Therefore, they cease to
be included costs. Furthermore, in step 3 of the RPM, all
included costs are divided into direct costs, indirect costs and
personal costs. Personal costs relate to marketing and selling
of project liquid. Direct costs relate to either the upstream
stage or the downstream stage whereas indirect costs must be
below a certain threshold and relate to the upstream as well as
the downstream stage (regulation 28 of the PRRTA Regulations).
Costs relating to an item of plant that has ceased to be used,
would not fall into any category of included costs. Capital
costs have amounts allocated for them in each year of tax during
the expected life of the unit of property to which they relate,
or (where they are deemed capital costs because they were
incurred before the production date) each year during the
expected life of the project, under regulation 36 of the PRRTA
Regulations. Costs for an item that has ceased to be used are no
longer included costs and so no further amount will be allocated
for them in years in which the unit of property is no longer
used (the Explanatory Statement, explanation to regulation 36).
83. As stated in paragraph 81 of this Ruling, the RPM is a
method to calculate a transfer price for project sales gas which
is used to ascertain the assessable petroleum receipts of a
taxpayer in relation to that gas. Sale proceeds from an item of
plant that has ceased to be used in the integrated GTL operation
do not form part of the RPM price calculation process. This does
not mean that the proceeds from the sale of an item of plant are
not subject to PRRT. The sale proceeds may be themselves
included in the assessable receipts of the taxpayer under
another provision of the PRRTAA (for example, section 27 of the
PRRTAA) rather than through any application of the RPM method to
project sales gas.
Allocation of capital costs
84. Capital costs are defined in regulation 31 of the PRRTA
Regulations and include costs that are for a unit of property
that is a depreciating asset for the purposes of section 40-30
of the ITAA 1997. Costs of marketing and selling project liquid
cannot be capital costs: they are personal costs of the
particular taxpayer, taken into account only in working out the
netback price component of RPM under regulation 23 of the PRRTA
Regulations. Included costs (refer to paragraph 81 of this
Ruling) that are incurred in a year of tax prior to the year of
tax in which project sales gas is first processed into project
liquid in the integrated GTL operation are treated as capital
costs. Included costs relating to depreciating assets (as
defined in section 40-30 of the ITAA 1997) are also capital
costs, whether incurred before the first year in which project
sales gas is processed into project liquid of the integrated GTL
operation or later.
85. Capital costs are augmented or reduced if regulations 33 to
35 of the PRRTA Regulations apply to them. Step 10 of the RPM
(regulation 25 of the PRRTA Regulations) requires an annual
allocation of capital costs (made according to regulation 36 of
the PRRTA Regulations). The formula for the allocation depends
on the expected operating life of the unit of property to which
the cost relates (for costs incurred for a depreciating asset
for section 40-30 of the ITAA 1997), or on the expected
operating life of the integrated GTL operation (for costs which
are treated as capital costs only because they were incurred
before the year the integrated GTL operation first produced
project liquid from project sales gas) (subregulations 36(2) and
36(7)). This annual allocation is used to calculate a cost-plus
price and a netback price for project sales gas (step 13 of the
RPM in regulation 25). The formulae for the calculation of
cost-plus price and netback price require that the annual
allocation of capital costs for the upstream stage and the
downstream stage be multiplied by a volume coefficient
(regulations 22 and 23 of the PRRTA Regulations).
86. The volume coefficient is defined in regulation 10 of the
PRRTA Regulations. The numerator in the formula for the volume
coefficient is the volume of project natural gas in the relevant
year of tax. The denominator in the formula for the volume
coefficient is the estimated average annual volume of project
natural gas, defined in regulation 9 of the PRRTA Regulations
(if the current year is before the base year, as defined in
regulation 10); the volume of project natural gas used to
produce project liquid in the year of tax (if the current year
is the base year); or average annual volume of project natural
gas used to produce project liquid since the base year (if the
current year is after the base year).
87. The volume coefficient ensures that in calculating the
cost-plus and netback prices a higher amount for capital costs
is taken into consideration in the years when a higher volume of
project natural gas is produced compared to the estimated
average volume of project natural gas or, if actual production
for any year has ever been higher, the achieved average volume
from that year (refer to Example 6 at paragraph 39 of this
Ruling). A lower amount for capital costs is taken into
consideration in the years when a lower volume of project
natural gas is used. The volume coefficient only affects the
amount for capital costs taken into consideration when
calculating the cost-plus and netback prices for a particular
year. The apportionment of costs by using the energy coefficient
(for each phase) affects these amounts for capital costs as well
as operating costs.
88. Project natural gas of an integrated GTL operation is
defined in subregulation 4(2) of the PRRTA Regulations as the
petroleum (natural gas) recovered from the project from which
sales gas will be produced and processed into project liquid.
Project natural gas therefore includes all of the petroleum that
is recovered in gaseous state (for example, pentane and hexane),
or as gas dissolved in liquid, from the petroleum project from
which project liquid will be produced (the term 'petroleum
(natural gas)' is not the same as what is commercially known as
'natural gas'). Natural gas used up in the production and
processing within that operation is included in the definition
of project natural gas.
89. In a typical integrated GTL operation, petroleum is
recovered in gaseous and liquid form. The gaseous petroleum is
project natural gas; the liquid petroleum is other petroleum.
Some natural gas is dissolved in the liquid petroleum stream and
may be released by heating the liquid stream. This gas may be
used as fuel or it may join the mainstream natural gas flow to
be processed into sales gas and then project liquid. Where no
natural gas is taken out of the operation for non-project
purposes, all of the natural gas, whether recovered in gaseous
form or initially dissolved in the liquid petroleum, will meet
the definition of project natural gas (subregulation 4(2) of the
PRRTA Regulations). Refer to Alternative
view 3 at
paragraph 105 for an alternative view and an analysis of that
view.
90. As discussed in paragraph 75 of this Ruling, the recovery of
petroleum is the start of the upstream stage and is always a
phase point. In a typical integrated GTL operation the costs of
the first phase are apportioned between the initial gas stream,
which is project product (project natural gas), and other
petroleum (the liquid stream minus project natural gas dissolved
in it). The project natural gas dissolved in the liquid
petroleum is not likely to be separated until a later phase (the
point where liquid and gas stream are separated will be a phase
point). As all of the project natural gas enters the first phase
its energy content must be included in the energy content of
project product entering the phase.
91. It may not be practicable for a taxpayer to measure the
energy content and volume of project natural gas at the start of
the upstream stage. The Commissioner will accept the measurement
of energy content and volume of project natural gas at any other
point (such as the end point, commonly at the slug catcher) in
the phase or even in a later phase provided all of the project
natural gas recovered from the project is included in this
measurement. For example, a taxpayer can measure the volume of
project natural gas at the point where the liquid stream and the
gas stream are separated and add to it the volume of project
natural gas recovered from the liquid stream (assuming that no
natural gas is taken for use as fuel or vented prior to these
points; alternatively, those volumes would also be added to it).
This principle can also be applied to measuring other gas and
liquid volumes.
92. Regulation 9 of the PRRTA Regulations requires that in the
year before the production year, the relevant taxpayers should
give to the Commissioner the estimate of the operating life of
the operation (N) and of the total volume of project natural gas
to be recovered during the life of the operation (VNG). As
discussed in the preceding paragraphs, natural gas used as fuel
or vented in an integrated GTL operation and natural gas
recovered from the liquid stream are included in the actual
volume of project natural gas. Since VNG is the estimate of the
total volume of project natural gas to be recovered during the
life of the operation, it should take into consideration all of
the natural gas that is expected to be recovered from the
project. This should be both what is already in gaseous form as
well as the gas dissolved in liquid petroleum. Although VNG is a
reasonable estimate, the taxpayer must take reasonable care in
considering all of the information available in making this
estimate. Subregulation 9(4) requires that if the estimate for N
or VNG changes (when new information becomes available), the
revised estimate of N or VNG must be communicated to the
Commissioner. VNG is not the same as the expected optimum level
of annual production times the number of years in the operating
life of the operation. It arrives at estimated average annual
volume of project natural gas from the total volume estimated to
be produced over the life of the project and the total estimated
life of the project, rather than the other way round.
93. The estimated average annual volume of project natural gas
calculated from the estimates of N and VNG is compared to the
actual volume of project natural gas processed in the operation
to determine the base year, the year in which the actual volume
of project natural gas first exceeds the estimated average
annual volume (regulation 10 of the PRRTA Regulations). In a
typical integrated GTL operation the actual volume of project
natural gas will be lower in the starting years and increase,
falling again towards the end of the life of the operation.
Therefore, the estimated average annual volume of project
natural gas will probably be less than the optimum level of
production. Multiplying the optimum level of production with the
estimated life of the operation to calculate VNG will give a
higher estimate of VNG. This method of estimating VNG will not
be a reasonable estimate of VNG (refer to Example 6 at paragraph
39 of this Ruling).
Measurement of gas and liquid volumes
94. The PRRTA Regulations do not specify any units of
measurement for gas and liquid volumes. The discussion on
regulation 37 of the PRRTA Regulations (calculation of the
energy coefficient) in the Explanatory Statement states that
where the International System of Units is used, the energy
content is measured in gigajoules at a temperature of 15 degrees
Celsius and one atmosphere pressure. As the Explanatory
Statement does not refer to any unit for measuring gas and
liquid volumes, the Commissioner will accept any standard unit
that is used in the petroleum industry to measure the gas and
liquid volumes provided it is used consistently across the whole
operation over the life of the operation. This is because there
are a number of formulae prescribed in the PRRTA Regulations and
for these formulae to operate properly, it is necessary that the
measurement of gas and liquid volumes is consistent across the
operation. Where a taxpayer needs to change the unit of
measurement for operational reasons, the taxpayer should request
an approval of the new unit of measurement from the Commissioner
and should convert all measures used thereafter in any
applicable ratios under the PRRTA Regulations to the new unit
(refer to Example 9 at paragraph 42 of this Ruling).
95. Project product is defined in subregulation 4(5) of the
PRRTA Regulations. Project product consists of project natural
gas of the integrated GTL operation (from which sales gas will
be produced and processed into liquefied product within the
operation), project sales gas (produced from project natural gas
and which will be processed into liquefied product within the
operation) and all liquefied products derived from project sales
gas (for example, LNG, LPG, liquefied ethane, liquefied propane
and liquefied butane) (regulation 4 of the PRRTA Regulations). A
typical integrated GTL operation will produce liquefied methane,
liquefied ethane, liquefied propane and liquefied butane as
project liquid. While methane is the main constituent of LNG,
the other three may be sold separately; mixed with other MPCs
(for example, with LNG or condensate); mixed together and sold
(for example, as LPG); or used as fuel or refrigerant. Some of
the project liquid may evaporate and the gas produced by the
evaporation may be vented, used as fuel or compressed and
re-liquefied. As discussed in previous paragraphs of this
ruling, venting and use as fuel in the integrated GTL operation
is use in the integrated GTL operation.
96. PLVal is defined in subregulation 23(1) of the PRRTA
Regulations as the total market value of the project liquid
produced in a year of tax in an integrated GTL operation. As
discussed in the previous paragraph, project liquid includes
liquefied methane, liquefied ethane, liquefied propane and
liquefied butane. Therefore, the market value of all of these
liquefied products produced in a year of tax is relevant in
calculating PLVal (refer to Example 7 at paragraph 40 of this
Ruling). In determining the assessable petroleum receipts from
an MPC, section 24 of the PRRTAA generally takes into
consideration the receipts from the sale of an MPC and the
market value of the MPC that becomes an excluded commodity by
further processing. This principle does not apply to project
liquid because project liquid is not an MPC: it and its
components have been produced from the relevant MPC (project
sales gas) and so are excluded from being MPCs ('marketable
petroleum commodity', section 2 of the PRRTAA). The relevant MPC
is project sales gas that becomes an excluded commodity by being
moved into further processing into project liquid. All of the
project sales gas processed in the integrated GTL operation in a
year of tax becomes an excluded commodity, and the market value
of all the project liquid produced in the same assessment year
must be included in the calculation of the RPM price
irrespective of whether the project liquid is sold that year or
not.
97. The market value of project liquid can be determined by
adding to (or subtracting from) the sale proceeds for project
liquid, the market value of any change in the volume of project
liquid in storage. The change in the volume of project product
in storage can be calculated practically by measuring the liquid
volume in the liquefied product storage tanks at the start and
the end of a year of tax. Since different liquefied gases that
are included in project liquid have different boiling points, it
is practical for them to be stored in separate tanks. Therefore,
all sales of project liquid and changes in the liquid volume in
all the storage tanks for all the products that constitute
project liquid of the integrated GTL operation must be taken
into consideration when calculating PLVal (refer to Example 8 at
paragraph 41 of this Ruling).
98. In some cases, a part of project liquid may be mixed with
another MPC that is not project product (even with condensate).
Sale proceeds from such a mixture should be apportioned between
project product and other MPC so that an appropriate amount for
the project liquid sold as a mixture with another MPC is
included in PLVal.
99. PRRT instalments (notional tax amount) of a taxpayer are
calculated in accordance with Part 6 of the PRRTA Regulations.
The formulae prescribed in regulations 39 and 40 of the PRRTA
Regulations also require a taxpayer to calculate the value of
their share of project liquid for the current year of tax and/or
the value of their share (or the predecessor owner's share) of
the project liquid for the previous year of tax. The above
discussion is equally relevant to the calculation of PLValprev,
the value of project liquid in regulations 39 and 40.
Appendix 2 - Alternative views
|
This
Appendix sets out alternative views and explains why
they are not supported by the Commissioner. It does not
form part of the proposed binding public ruling. |
100. Alternatives views relating to the issues discussed in the
Explanation section of this Ruling have been considered in this
section. The reasons the Tax Office considers the alternative
views to be incorrect are explained in the 'Analysis' following
each alternative view.
Measurement of the volume of project sales gas for the
purposes of regulation 17 of the PRRTA Regulations
Alternative view 1
101. In a typical integrated GTL project, project sales gas
comes into existence at the end of 'Removal of impurities'
stage. When impurities are removed from natural gas it becomes
sales gas. At the end of the 'Removal of impurities' stage, the
gaseous mixture may still be a combination of condensate and
sales gas. Nevertheless, the end of 'Removal of impurities'
stage is the PRRT ring fence for the purposes of determining
assessable petroleum receipts.
Analysis
102. At the end of the 'Removal of impurities' stage as
described, the gaseous mixture consists of methane, ethane,
propane, butane, pentane and hexane and possibly other heavier
hydrocarbons and minute quantities of impurities (many of which
would not separately be gaseous at 15°C and a pressure of one
atmosphere). Presence of pentane and hexane in the gaseous
mixture generally means that the mixture cannot meet the
definition of project sales gas because the substance would not
be in a gaseous state at 15°C and one atmosphere, a condition in
the definition of sales gas (refer to paragraph 55 of this
Ruling). The presence of any significant amount of pentane and
hexane in the gaseous mixture is also likely to mean, in
practice, that the mixture has not yet been fully processed so
as to be ready for use as a feedstock for conversion to project
liquid, as that conversion normally is by a process that can
only be carried out on a mixture of gases that does not include
any significant amounts of pentane, hexane, or heavier
hydrocarbons. Under the PRRTAA, assessable petroleum receipts
arise when petroleum is sold or an MPC produced from petroleum
becomes an excluded commodity (for example, by sale or further
processing). Sales gas and condensate are included as separate
items in the definition of MPC in section 2 of the PRRTAA.
However, a mixture of these two items would not ordinarily meet
the definition of either MPC (though, if it did so, any further
MPC produced from the mixture is to that extent excluded from
being an MPC). In an integrated GTL operation sales gas will
usually become an excluded commodity by being moved from its
place of production for further processing. This can generally
only happen after sales gas and heavier substances (potentially
forming part of condensate) have been separated.
Measurement of gas and liquid volumes
Alternative view 2
103. PLVal should only include the sale proceeds for LNG. The
volume of project liquid in the tank does not become an excluded
commodity until it is sold. Therefore, it should not be taken
into consideration. Where some of the liquefied ethane,
liquefied propane or liquefied butane is added into condensate,
the MPC sold is condensate, not LNG. Therefore, there is no
requirement to include part of the sale proceeds of condensate
in PLVal.
Analysis
104. In a typical integrated GTL operation sales gas is the
relevant MPC that becomes excluded commodity when it is moved
into the downstream stage for processing into project liquid.
The definition of MPC in section 2 of the PRRTAA includes sales
gas. A product produced from another MPC cannot be an MPC.
Project liquid is not an MPC because it is produced from sales
gas that is itself an MPC. Therefore, it is the completion of
the production of sales gas, at the end of the upstream stage,
that triggers the need to calculate assessable petroleum
receipts. The sale of project liquid (processed from project
sales gas) does not trigger the calculation of assessable
petroleum receipts for the purposes of an integrated GTL
operation. Therefore, it is reasonable and appropriate that the
total quantity of project liquid produced in a year of tax,
including the quantity that is not sold (and reduced by a
reduction in project liquid on hand, as this reflects sale from
earlier years' production), is relevant to the calculation of a
netback price in regulation 23 of the PRRTA Regulations.
Apportionment of costs between project product and other
petroleum commodities
Alternative view 3
105. Pentane and heavier hydrocarbons present in the gas stream
along with a range of impurities in the 'Removal of impurities'
stage cannot be treated as part of project natural gas. What is
commercially known as 'natural gas' does not contain pentane and
heavier hydrocarbons. Natural gas is only sales gas with
impurities such as carbon dioxide, hydrogen sulphide, water and
nitrogen. If the commercial meaning of 'natural gas' is used,
the gas stream in the 'Removal of impurities' stage should be
treated as a mixture of natural gas and condensate and costs
apportioned accordingly.
Analysis
106. Natural gas has not been defined in the PRRT legislation.
However, project natural gas has been defined in subregulation
4(2) of the PRRTA Regulations as the petroleum (natural gas) of
the project from which sales gas will be produced and processed
into liquefied product. The commercial meaning of a term can be
used provided the term has not been defined in the legislation.
The words 'petroleum (natural gas)' are not the same as 'natural
gas'. Petroleum (natural gas) includes all of the petroleum that
is recovered in gaseous state, or as gas dissolved in liquid,
from the petroleum project.
Appendix 3 - Detailed contents list
107. The following is a detailed contents list for this Ruling:
|
|
Paragraph |
|
What this Ruling is about |
1 |
|
Background |
2 |
|
Ruling |
12 |
|
Measurement of the volume of project sales
gas for the purposes of regulations 16 and 17 |
12 |
|
Apportionment of costs between project
product and other petroleum commodities |
17 |
|
Allocation of capital costs |
25 |
|
Measurement of gas and liquid volumes |
28 |
|
Examples |
33 |
|
Measurement of the volume of project sales
gas for the purposes of regulation 17 of the PRRTA
Regulations |
33 |
|
Example 1 |
33 |
|
Apportionment of costs between project
product and other petroleum commodities of the petroleum
project |
34 |
|
Example 2 |
34 |
|
Apportionment of costs between project
product and other petroleum commodities of the petroleum
project |
36 |
|
Example 3 |
36 |
|
Apportionment of costs between project
product and other petroleum commodities |
37 |
|
Example 4 |
37 |
|
Identification of upstream and downstream
costs |
38 |
|
Example 5 |
38 |
|
Allocation of capital costs |
39 |
|
Example 6 |
39 |
|
Measurement of gas and liquid volumes -
calculation of PLVal |
40 |
|
Example 7 |
40 |
|
Measurement of gas and liquid volumes - LPG
gases |
41 |
|
Example 8 |
41 |
|
Measurement of gas and liquid volumes - use
of Standard Cubic Metres |
42 |
|
Example 9 |
42 |
|
Date of effect |
43 |
|
Appendix 1 - Explanation |
44 |
|
The processes in an integrated GTL
operation |
44 |
|
Some relevant definitions |
54 |
|
Measurement of the volume of project sales
gas for the purposes of regulations 16 and |
17 |
|
of the PRRTA Regulations |
58 |
|
Apportionment of costs between project
product and other petroleum commodities |
72 |
|
Allocation of capital costs |
84 |
|
Measurement of gas and liquid volumes |
94 |
|
Appendix 2 - Alternative
views |
100 |
|
Measurement of the volume of project sales
gas for the purposes of regulation 17 of the PRRTA
Regulations |
101 |
|
Alternative
view 1 |
101 |
|
Analysis |
102 |
|
Measurement of gas and liquid volumes |
103 |
|
Alternative
view 2 |
103 |
|
Analysis |
104 |
|
Apportionment of costs between project
product and other petroleum commodities |
105 |
|
Alternative
view 3 |
105 |
|
Analysis |
106 |
|
Appendix 3 - Detailed
contents list |
107 |
Previous Draft:
TR 2008/D4
References
ATO references:
NO 2007/19050
ISSN: 1039-0731
Related Rulings/Determinations:
TR 2006/10
Subject References:
liquefied petroleum gas
marketable petroleum commodities
petroleum resource rent tax
PRRT assessable petroleum receipts
sales gas
transfer pricing
Legislative References:
PRRTAA
PRRTAA 2
PRRTAA 21
PRRTAA 23(1)
PRRTAA 24
PRRTAA 24(1)
PRRTAA 24(1)(b)
PRRTAA 24(1)(d)
PRRTAA 24(1)(e)
PRRTAA 25
PRRTAA 27
PRRTAA Div 3
PRRTA Regulations
PRRTA Regulations 3
PRRTA Regulations 4
PRRTA Regulations 4(1)
PRRTA Regulations 4(2)
PRRTA Regulations 4(3)
PRRTA Regulations 4(4)
PRRTA Regulations 4(5)
PRRTA Regulations 5
PRRTA Regulations 6
PRRTA Regulations 6(1)(a)
PRRTA Regulations 6(1)(b)
PRRTA Regulations 7
PRRTA Regulations 7(1)
PRRTA Regulations 7(2)
PRRTA Regulations 7(3)
PRRTA Regulations 7(4)
PRRTA Regulations 7(5)
PRRTA Regulations 7(6)
PRRTA Regulations 8
PRRTA Regulations 9
PRRTA Regulations 9(4)
PRRTA Regulations 10
PRRTA Regulations 14
PRRTA Regulations 14(2)
PRRTA Regulations 14(3)
PRRTA Regulations 15
PRRTA Regulations 15(2)
PRRTA Regulations 15(3)
PRRTA Regulations 16
PRRTA Regulations 16(1)(a)
PRRTA Regulations 16(1)(b)
PRRTA Regulations 16(2)(a)
PRRTA Regulations 16(3)(a)
PRRTA Regulations 17
PRRTA Regulations 17(1)(a)
PRRTA Regulations 17(1)(b)
PRRTA Regulations 17(2)
PRRTA Regulations 17(3)
PRRTA Regulations 20
PRRTA Regulations 21
PRRTA Regulations 22
PRRTA Regulations 23
PRRTA Regulations 23(1)
PRRTA Regulations Pt 5
PRRTA Regulations 25
PRRTA Regulations 27
PRRTA Regulations 28
PRRTA Regulations 28(3)
PRRTA Regulations 28(4)
PRRTA Regulations 28(5)
PRRTA Regulations 28(7)
PRRTA Regulations 29
PRRTA Regulations 30
PRRTA Regulations 31
PRRTA Regulations 32(4)
PRRTA Regulations 33
PRRTA Regulations 34
PRRTA Regulations 35
PRRTA Regulations 36
PRRTA Regulations 36(2)
PRRTA Regulations 36(7)
PRRTA Regulations 37
PRRTA Regulations Pt 6
PRRTA Regulations 39
PRRTA Regulations 40
PRRTA Regulations 40(2)
PRRTA Regulations 40(3)
ITAA 1997 40-30
Offshore Petroleum Act 2006 6
TAA 1953
Other References
Explanatory Statement, Select Legislative Instrument 2005 No.
329
|